Building Projects
Business Units, Twechar
Client: Strathkelvin Developments Ltd.
Value: £1.3m
Contract: Scottish Building Contractors with Contractors Design
Contract Period: 25 weeks
Architect: Dallman Johnstone
Engineer: Roy Easton & Company
Please click on a thumbnail to view
Project Description:
Construction of 6 business units, four of which have a precast concrete mezzanine floor office space, accessed by a precast concrete stair.
The structural steel frame, on reinforced concrete founds, has insulated cladding to walls and roof.
The front wall has feature brickwork up to first floor. Vehicle access is via manually operator "up & over" garage doors.
Works Included:
- Removal of peat
- Reinforced foundations
- Retaining walls
- Drainage 750 diameter concrete pipes
- Polished floor slabs
- Street lighting
- Fencing
- Landscaping
- New water mains