Langside College
Client: Langside College
Main Contractor: Balfour Beatty Construction
Quantity Surveyor: Currie and Brown
CDM Coordinator: Doig and Smith
Value: £900k
Contract Period: 22 weeks
Contract: SBCC
Please click on a thumbnail to view
Project Description:
Enabling and Substructure packages as part of the new college.
Works Included:
- Cut and fill exercise involving the disposal of 4500m3 offsite and 2500m3 of imported material
- Formation of haul road and temporary car park
- Pile caps and ring beams
- Concrete floor slab
- Construction of retaining walls
- Installation of ducting and drainage