Civils Projects

Langside College

Client: Langside College
Main Contractor: Balfour Beatty Construction
Quantity Surveyor: Currie and Brown
CDM Coordinator: Doig and Smith
Value: £900k
Contract Period: 22 weeks
Contract: SBCC

Please click on a thumbnail to view

Project Description:

Enabling and Substructure packages as part of the new college.

Works Included:

  • Cut and fill exercise involving the disposal of 4500m3 offsite and 2500m3 of imported material
  • Formation of haul road and temporary car park
  • Pile caps and ring beams
  • Concrete floor slab
  • Construction of retaining walls
  • Installation of ducting and drainage