Luddon are once again looking forward to working with Morgan Sindall having been awarded a £1.5m package of works on the new Maryhill Health Centre Project in Glasgow.

The £12m project will provide the local community with four GP Practices as well as consulting rooms for a variety of community health services including physiotherapy, Podiatry, mental health, dental, district nursing etc.

Our package of works includes the site set up and enabling works which were carried out in December last year and we have returned from the festive break refreshed and ready to commence the main groundwork elements. The nature of the site offers some interesting logistical challenges, being tightly confined and split over 2 levels.

The 42 week programme of works consists of bulk earthworks and construction of concrete retaining walls, installation of drainage and concrete foundations. Hard landscaping elements including gabion baskets, granite slabs and monoblocks, will add to the aesthetics of the external approaches to the health centre.