Client: SP Energy Networks
Value: £620k
Contract: NEC 3 Option B
Project Description:
Demolition and civils works for super grid transformer replacement
Works Included:
- Demolition of existing structures
- Construction of new reinforced concrete transformer bunds
- New reinforced concrete pad foundations
- Installation of new oily water drainage system including interceptor and isolation manholes
- New cable troughs and HV ducting
- Refurbishment of existing trough system including fitting new lids
- Excavation & Installation of earthing grid
- Installation of new SPEN specification HV compound fencing
- Construction of “Black Start” generator and fuel tank bases, ductwork and earthing