Johnstone Sub Station Enabling Works

Client: Scottish Power / Iberdrola

Value: £170k

Project Description:

Enabling works for Johnstone 132/32kv T1/T2 Transformer replacement

Works Included:

  • Repair  the existing reinforced concrete disconnector support structure.
  • Replacement of concrete trench covers with m/d solid top GRP covers.
  • Internal brickwork to the LVAC room of the control building and bricking up of window and door openings
  • Formation of new external/internal openings to control building
  • New access road into the existing substation.
  • Removal of existing concrete foundations/slabs and installation of a new skid  slab 
  • Capping of all drainage and services prior to demolition of the existing oil plant and LVAC building.
  • New foundations and brick piers to strengthen the existing boundary wall.
  • New access road and pedestrian access path
  • Services  installations  including  heating,  lighting,  small  power,  ventilation  and alarm systems
  • Removal  of part of boundary wall and installation of new security gate
  • Installation of steel plates at the new vehicle access gate