Linwood Point Car Park Paisley

Client: Group First

Value: £406k

Contract: SBCC Minor Works with Contracts Design

Project Description:

Construction of new 167 space car park plus associated earthworks, drainage and street light works

Works Included:

  • Site Clearance
  • Bulk excavation (9000m3)
  • Installation of 150mm dia  drainage pipes protected with concrete cover slabs
  • Installation of new concrete manholes
  • Concrete kerbs
  • 80mm permeable block paving to parking bays as part of SUDS drainage system laid on graded stone and membrane filtration system with flow control into main sewer
  • Asphalt surfacing to access road
  • White lining
  • Soft landscaping and seeding
  • Street lighting works.