New Cumnock Sub Station Civils

Client: Scottish Power/ IEC

Value: £250k

Contract: NEC 3 Option B with amendments

Project Description:

Construction of new transformer bund within the 275/132kV Substation

Works Included:

  • Temporary fencing
  • Excavation and formation of 450mm thick slab foundation
  • Cast in situ reinforced concrete transformer bund (26m x 15m x 1m deep)
  • Cast in situ reinforced concrete transformer bases
  • Trench and duct installation
  • Installation of high frequency earth rods including CAD welding
  • Oily water drainage systems
  • Site reinstatement
  • Surface chipping

< Back to projects