Out of Plastics Project, Wellpark Brewery

Client: Tennents Caledonian Breweries Ltd

Value: £398k

Contract: SBCC Minor Works with quantities

Project Description:

Shell works within existing packaging hall to enable new plant and machinery fit out

Works Included:

  • Take down and remove existing personnel doors and roller shutter doors
  • Blockwork wall to fill void from roller shutter door
  • Application of new resin finish to the existing floor
  • Internal and external metal cladding works
  • Saw cutting to form 3m x 5m opening in existing 200mm thick concrete ceiling/floor 7m high to enable fitting of new carousel between the 2 floors
  • Excavation to form four new lift pits
  • Installation of new high speed roller shutter doors and fire doors
  • Mechanical and electrical works including laser smoke detection system
  • Painting the existing walls and ceilings