Client: Glasgow Airport Ltd
Value: £62k
Contract: BAA Works Contract with BAA Works Terms Option A V1.1 (similar to NEC option A)
Project Description:
Construction of a safe route to walk from the Ramada Hotel to Glasgow Airport terminal building
Works Included:
- Set up traffic management in various phases
- Excavate grass/soft landscaping in verges and construct new footway
- Install new puffing crossing including ducts, chambers and new power supply
- Alteration of existing road markings to suit new puffin crossing
- Installation of pedestrian barriers
- Alteration of islands and road markings within existing car park to form a safe route to terminal building