Client: Scottish Canals
Value: £141k
Contract: NEC 3
Project Description:
Upgrade of existing surfaced towpath with new granite setts, granite kerbs, drainage, ducting, lighting and graffiti removal works
Works Included:
- Fully close off the existing towpath both to the East and West of the proposed site and provide a diversion around the works for public use
- Removal of existing vegetation from the stone copes
- Removal of barrier gates and speed humps
- Scarify/break out the existing surfacing to allow new towpath construction
- Reduce side walls of redundant canal abstraction point and fill the existing void with concrete
- Install three 100mm, flexible ducts, with draw cords in canal bank soft verge along with 3 chambers (500 x 500mm square and 500mm deep), connected to the ducting, to allow access for future cabling
- Supply and install new water supply pipework (32mm diameter barrier pipe with 20mm barrier pipe branch) connections to proposed location of new service bollards
- Supply and lay new granite kerbs to towpath edge
- Supply and lay new granite delineation kerb to back edge of towpath
- Supply and lay new dark grey granite setts, setts laid on 30mm mortar with 150mm type 1 sub-base
- Install metal pin mooring rings
- Install new solar LED lights and recessed uplighters along towpath
- Graffiti removal from Viewforth Bridge walls and abutment