Client: Scottish Canals
Value: £80k
Contract: NEC 3 Option C
Project Description:
Construction of a canal boat support structure within the Monkland Canal at Summerlee Heritage Museum
Works Included:
Construction of a concrete and steel support structure within the Monkland canal at the Summerlee Heritage Museum to support the restored Vulcan canal boat. Procure crane, prepare lifting area to crane supplier’s requirements and carry out the lift to place the canal boat into position. Fit new galvanised access gangways. Installation of power supply to the boat