50,000ft² Warehouse

Client: Forth Ports Ltd

Contract: NEC 3 Option A

Project Description:

Design and Build of a 50,000ft²  facility for the storage of fish meal 

Works Included:

  • Formation of asphalt access road
  • Formation of concrete hardstanding
  • Formation of pile mat
  • Installation of 136no 250sq concrete friction piles
  • Installation of ring beam foundations
  • Installation of storm surface water drainage system
  • Erection of 240t of structural steelwork
  • Erection of single skin clad roof and walls
  • Installation of pedestrian doors and vehicle access doors
  • Installation of perimeter precast concrete push walls and internal precast concrete rocket walls.
  • Installation of mechanical and electrical works including lighting, fire main and fire alarm system
  • Installation of concrete floor slab
  • Installation of industrial PVC curtain