Trafford Waters, Phase 1 Infrastructure

Client: Peel L&P Developments Ltd.

Value: £6.2m

Contract: NEC 4 Eng & Construction Contract, June 2017 Option A

Project Description:

Design and construction of the enabling infrastructure for the first phase.

Works Included:

  • Forming a new two way junction
  • Road alignment works
  • Creation of a right hand filter lane
  • Bulk earthworks
  • D&B of new primary and secondary roads
  • Civils associated with street lighting
  • New footpaths and cycleways
  • Drainage works
  • Hard and soft landscaping
  • Traffic management, utility works and service diversions managed by Ameon Utilities. On site civils only in our scope